One of the biggest misconceptions in residential construction is that "the person who drew the house" is automatically responsible for every document needed for permitting. In reality, a permit package can combine work from several professionals, contractors, manufacturers, and agencies.
Residential Designer / Architectural Professional
This role commonly develops the building layout, floor plans, elevations, sections, and architectural details. Depending on the project, licensing requirements, and scope, an architect or other qualified professional may be involved. The key point for the owner is to define exactly what the design contract includes — and what it excludes.
Structural Engineer
The structural engineer may design foundations, framing systems, beams, columns, connections, and other structural components. Florida projects also require appropriate consideration of project-specific wind and other design loads.
Surveyor
A licensed surveying professional prepares survey documents within the contracted scope, establishing boundary and site information that the design team can use for building placement and coordination.
Mechanical / HVAC Professional
Mechanical documentation can involve HVAC load calculations, equipment selection, duct design, and related permit information. Some jurisdictions specify recognized ACCA calculation methods for new residential work.
Electrical and Plumbing Design
Electrical and plumbing documentation may be prepared or supported by appropriately qualified design professionals and/or licensed trade contractors depending on the project, jurisdiction, and legal scope. Owners should not assume those disciplines are automatically included in an architectural design agreement.
Energy-Compliance Provider
Energy calculations may be prepared using approved Florida compliance methods or software by professionals familiar with the project's envelope and mechanical information. These documents must coordinate with the actual permit plans.
Truss Manufacturer / Truss Engineer
When engineered trusses are used, the truss package is typically developed as delegated engineering based on the building geometry, loads, and support conditions provided by the project team. Jurisdictions may require truss engineering as part of the permit review. Orange County, for example, expressly lists it when applicable.
General Contractor
The contractor's role is not simply to build from whatever drawings arrive. A competent contractor reviews the package for constructability, scope coordination, permitting needs, trade sequencing, and field conflicts. The contractor also coordinates subcontractors, permit processes, inspections, and changes within the limits of the contractor's licensed role.
Building Department and Other Agencies
The building department does not design the project. It reviews the submitted information under the applicable regulatory process. Depending on the property, zoning, development engineering, utilities, health, environmental, or floodplain reviewers may also be involved.
The Owner's Most Important Question
Before paying for a plan package, ask each consultant what deliverables are included. A contract that says "house plans" may not mean electrical design, HVAC, energy calculations, survey, truss engineering, site plan, septic documentation, or permit coordination are included.
A3MS Coordination Checklist
- Who owns the architectural scope?
- Who owns structural engineering?
- Who provides the survey and site information?
- Who prepares HVAC calculations and duct design?
- Who provides electrical and plumbing permit information?
- Who prepares energy calculations?
- Who provides truss engineering?
- Who coordinates the complete permit submission?
- Who responds to plan-review comments?
A3MS Takeaway
Permit packages fail when responsibilities fall into the gaps between consultants. The strongest approach is to define ownership of every required deliverable before the project reaches permit submission.
Authoritative References
- Orange County — New Residential Structure Permit
- Seminole County — Master Building & Engineering Permit Process
AvisoDisclaimer
General educational information only. Permit, design, engineering, and documentation requirements vary by jurisdiction, project scope, property conditions, and the code edition in effect at permit submission. Research verified August 21, 2026. The Florida Building Commission currently identifies the 8th Edition (2023) Florida Building Code as effective December 31, 2023 and publishes development materials for the 9th Edition (2026); verify whether the applicable code edition or local checklist has changed before use.